Legal Considerations When Establishing a U.S. Facility

Evaluate a proposed site against the actual production process and the date operations must begin. Before making an unconditional commitment, establish a credible path to lawful use, sufficient utilities, and environmental approvals, then allocate the remaining risk in the lease or purchase agreement.

Evaluate the proposed use at the proposed address

An industrial zoning designation is a starting point. Give the local authority a concrete description of the planned use, including manufacturing steps, storage, building alterations, and vehicle access as relevant. A previous tenant’s apparent ability to operate does not establish that a new process or expansion is permitted. Confirm what approvals and inspections must occur before occupancy or operation, and ask whether the proposed schedule accommodates them.

Check utilities on the same timetable. Determine who can confirm peak electrical capacity, water supply, and wastewater service. A landlord may be willing to upgrade power, but the utility may control when the additional capacity is available. An agreement on who pays for the work leaves a scheduling gap unless the parties also address what happens if service is late.

Separate historic conditions from new operations

At a former manufacturing property, investigate potential contamination before acquisition. For a buyer seeking to qualify as a bona fide prospective purchaser under federal CERCLA, conducting all appropriate inquiries before purchase is one requirement. Continuing obligations can also apply after acquisition. Use the results to decide whether to investigate further, reallocate costs, or walk away while the agreement still allows it. Any indemnity from the seller should be evaluated separately from the buyer’s potential obligations to the government.

New operations raise a separate permitting question. The previous operator’s permit can show what was authorized, but it may not cover a new operator or a process with different emissions or discharge volumes. Identify the approvals that depend on the proposed construction and production process, then determine whether each approval can transfer, needs amendment, or requires a new application. If the answers will arrive after the lease is signed, put the timing risk in the lease.

Preserve room to resolve issues in the site agreement

Where an approval remains uncertain, negotiate access for diligence, a defined investigation period, cooperation in obtaining approvals, and the consequences if a necessary condition cannot be met. For a lease that calls for landlord work, specify when the premises will be considered delivered and when rent starts. A facility can be available for physical possession before it is ready to carry the power load or pass the inspections the business needs.

For a leased facility, also check who owns alterations and who must remove them when the lease ends. A production line that is expensive to disassemble can change the economics of a short term or an early termination.

Compare candidate locations by the earliest credible date for lawful operation and the cost of a delay. If a permitting decision or utility upgrade controls that date, address it before signing equipment orders or committing to a customer’s production schedule. This puts the terms of the site agreement in direct conversation with the operating plan.