Korea’s foreign investment cash grants depend on the investment plan and the commitments in the cash grant agreement. A change in spending or hiring may affect future instalments or expose payments already received to recovery. The effect depends on the applicable rules, the agreement and any authorized amendment.
Start with the signed commitments
The documents submitted with a grant application may contain assumptions about the business that differ from the milestones in the executed agreement. If equipment arrives late and hiring slips, identify the original delivery date, the date on which the company actually began hiring, and the measurement date the agreement uses. A delay against an internal forecast and failure to satisfy a contractual milestone are distinct facts. This distinction determines what the investor should ask the authority to change and what evidence supports the request.
Assess future payments and amounts already paid
The Enforcement Decree permits adjustment of instalment amounts or timing in light of a change in the investment plan or spending performance. The decree separately identifies grounds that can support cancellation, withdrawal, reduction or recovery, including false or improper applications, failure to perform obligations under the cash grant agreement, and an inability to continue the business during the contractual period because of circumstances such as closure or insolvency. Determine which legal basis is asserted and how the current operating rules and the agreement calculate any return. A reduction in a future instalment has a different cash impact from a demand to return money already spent.
Document a change while there is time to address it
A timing problem and a reduction in project scope call for different proposals. If the company can maintain committed investment but will start production late, a revised schedule can show what milestones remain achievable and when. If the revised project cannot support the promised employment level, moving an installment date may leave the underlying obligation unresolved.
When headquarters changes the capital budget, quantify the difference in eligible spending, expected staffing and completion dates. Explain which obligations can still be met and on what evidence. Discussions with a program official can help identify a path forward. The legal effect of a change should be assessed using the required approval and the effective contractual documents. Where a closure is being considered, model any potential grant repayment before forecasting the residual proceeds available to investors. Separate the company’s obligations to the grantor from assumptions about the remaining investment value.
The operating guidelines provide for full repayment in specified cases and shortfall-based repayment for certain investment or hiring failures. Where multiple measures apply, the largest applicable amount may control. The company should reconcile the agency’s measurement date and figures against the award and its actual performance. The guidelines generally provide an opportunity to cure and at least 14 days to respond, subject to exceptions. Under their transitional provisions, the revised recovery rules can also apply to existing awards, subject to more favorable terms in the signed grant agreement on the relevant point.
Sources
- 외국인투자 촉진법 제14조의2 — https://www.law.go.kr/법령/외국인투자촉진법/제14조의2
- 같은 법 시행령 제20조의3~4 — https://www.law.go.kr/LSW/lsInfoP.do?lsiSeq=284815
- 현금지원제도 운영요령 제18~20조 및 부칙 (산업통상부 고시 제2026-117호) — https://www.motir.go.kr/attach/down/debc2e19d8870bf491bf5e73464259e8/874bdd977fba0ffcc95966c047449aaa/778bdbf5db9ced7c8fd52756c00bf0cd