A force majeure clause should connect a defined external event to the obligation it actually prevents or delays. Its operation also depends on notice, reasonable alternatives, and the rights each party retains if the disruption continues.
Trace the event to the obligation
Suppose a government bans exports of a component that a supplier has agreed to deliver. Identify the goods and destinations the measure covers, its effective date, and the orders affected. Existing inventory or a permitted alternative source may change the analysis. If the original route merely became more expensive, the contractual test for relief may not be satisfied. The agreement should reflect whether the parties intend relief for prevention, serious hindrance, or delay, within the limits of applicable law.
New York decisions applying Kel Kim illustrate why the wording matters. A force majeure clause is narrowly construed, and the event said to excuse performance must fall within its scope. When a particular export restriction, port closure, or upstream supply dependency matters to the bargain, address it specifically and explain what forms of alternative performance remain feasible.
Give the other party enough information to respond
A buyer receiving notice may need to shift production or source elsewhere. A useful notice identifies the obligation affected, the expected duration if known, and the steps being taken to resume performance. The parties may require updates and reasonable efforts to overcome the disruption. They can also address partial performance so that a shortfall affecting one order does not trigger uncertainty about every shipment.
Where the main concern is a price spike, a separate price adjustment or renegotiation mechanism can speak directly to that risk. A clause designed for external impediments may leave ordinary increases in wages, materials or shipping costs with the party that agreed to perform.
Specify what the excuse changes
Under Article 79 of the CISG, a party may be exempt from damages if it proves that its failure was due to an impediment beyond its control that it could not reasonably have been expected to take into account at contracting or to avoid or overcome, including its consequences. The exemption operates while the impediment exists. The affected party must notify the other side of the impediment and its effect. If notice is not received within a reasonable time after the affected party knew or should have known of the impediment, it is liable for damages resulting from nonreceipt. Article 79 leaves remedies other than damages available subject to their own requirements.
Where Article 79(2) applies to a third party engaged to perform all or part of the contract, both the contracting party and that third party must satisfy Article 79(1). A supplier’s notice should identify the orders affected and address whether available stock or permitted alternatives can cover them. An agreement can set a commercial endpoint for a long interruption. For example, after an agreed period either party might cancel affected orders while leaving unrelated orders in place. The clause can also address the price due for goods already delivered. Test that drafting against a disruption that affects only part of the supply. If the parties can identify which dates and orders change, who must give notice and when the buyer can seek replacement supply, the provision will be easier to apply under pressure.
Sources
- Fives 160th v. Qing Zhao, 2021 NY Slip Op 31111(U) (N.Y. Sup. Ct. Apr. 6, 2021), 인용 Kel Kim, 70 N.Y.2d 900 (1987) https://www.nycourts.gov/reporter/pdfs/2021/2021_31111.pdf
- CISG art. 79 https://uncitral.un.org/sites/default/files/media-documents/uncitral/en/v1056997-cisg-e-book.pdf